Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 01/10/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Completed 2" Mill and Repave to fulfill moratorium requirements. |
| 12/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Remaining lane backfilled with ABC and paved. Completed. |
| 12/04/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Turn lane and south west bound lane backfilled with ABC and paved. |
| 12/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Old lead pipe pulled, new copper pipe installed with service switch over. East bound lanes - Backfilled with ABC and paved. Workers gone by 1:30 pm and barricades up. |
| 11/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Working in north lane of west bound traffic. Plated entire trench at completion. |
| 11/28/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Worked in center turn lane and 1st west bound lane, baerricades up. Flush plated open trench. Work ended before 1:30 pm |
| 11/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Excavated 2 trenches in 2 east bound lanes to expose existing lead srvice pipes and bed for new copper pipe. Installed traffic plates and remove barricades by 1:30 pm. |
| 11/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Barricades set early told contractor to hold to times listed on permit. East bound lanes closed to mill for flush traffic plates. |
| 11/20/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor called will start 11/26/18 |