Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 11/08/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Completed. |
| 11/01/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Apron forms stripped, barricades still up. |
| 10/31/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Drive apron formed, compacted, graded to correct depth, ready for concrete. Concrete placed and barricaded off. |
| 10/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Sidewalk ready for concrete - approved to pour. |
| 10/25/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Soil still very wet - no compaction. |
| 10/24/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Sidewalk formed and graded but had rain water standing. Need to dewater and re-conpact after drying. |
| 10/12/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pre-con at site, need barricades on south side - sidewalk closed. Already demoed sidewalk. |
| 10/11/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor called to set up pre-con for 10/12/18 at 7:30 am. |