Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T18RW04485

Parcel: 129101290

Inspection Status: Correction Required

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Permit Number - T18RW04485

Inspection Description - TDOT-EXCAV GENERAL INSPECTION

Inspection Status - Correction Required

Date Description Inspector Results Comments
02/19/2019 TDOT-EXCAV GENERAL INSPECTION Correction Required Repairs at large scupper not completed. Expired permit.
02/07/2019 TDOT-EXCAV GENERAL INSPECTION Continued Contractor said repairs will be completed week of 2/11/19. They asked if they can pull weeds along exit ramp from Kino - told them to call for permit.
01/23/2019 TDOT-EXCAV GENERAL INSPECTION Continued TDOT engineer approved the handrail at scupper fix. Told contractor that I will not approve the work until 2 items are corrected.
01/11/2019 TDOT-EXCAV GENERAL INSPECTION Continued Told contractor asphalt patch must be removed and replaced. Must have it inspected before placement. Confirmed by supervisor. Asphalt was placed without inspection during a cold and wet day.
Concrete spillway on west side of site inspected, modified by adding extra re-bar and removal of concrete debri. Approved for pouring.
12/27/2018 TDOT-EXCAV GENERAL INSPECTION Continued North parkinglot entry sidewalk poured and stripped.
12/14/2018 TDOT-EXCAV GENERAL INSPECTION Continued Scupper (main) damaged by contractor when he hit the welded on handrail. GC instructed to have engineer examine damage and come up with repairs.
12/13/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspect north entry curb - OK to pour.
12/11/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspect for sidewalk forms and subgrade - OK to pour.
12/10/2018 TDOT-EXCAV GENERAL INSPECTION Continued Poured single scupper and sidewalk.
12/06/2018 TDOT-EXCAV GENERAL INSPECTION Continued Single scupper to be removed - not correct
11/30/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspection the type 2 scupper - wrong needs R&R. sidewalk subgrade needs compaction. Correct slope at sidewalk. Incorrect sidewalk form at south ramp.
11/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspected type 3 scupper forms - slab/walls. Required rebar correction before pour.
11/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspect large scupper - fix rebar. Then OK to pour.
11/09/2018 TDOT-EXCAV GENERAL INSPECTION Continued Poured curb.
11/08/2018 TDOT-EXCAV GENERAL INSPECTION Continued Inspected additional curb to north parking lot.
10/25/2018 TDOT-EXCAV GENERAL INSPECTION Continued Engineer has grade all wrong needs re-design. Work stopped.
10/18/2018 TDOT-EXCAV GENERAL INSPECTION Continued Pre-con discussed SW and curbs and barricades. Contractor to call before pours.
Barricades up.
10/17/2018 TDOT-EXCAV GENERAL INSPECTION Continued Contractor called for pre-con for 10/18/18