| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved | Permanent patching will be completed under permit# T19RW00831 | |
| 02/12/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Temporary patches remain in place. Contractor notified of expiration New permit to be applied for to install permenant patches per French Cowen with Sundt. |
|
| 01/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Temporary patches remain in place | |
| 01/18/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Abandonements complete per Tucson Water Insp.Eric Quarrel Temporary patches remain |
|
| 01/15/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Work continues on water services Crew installing temporary patches on services completed. |
|
| 01/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew started waterline work. T-C set up. Crews sawcutting and potholing today. |