Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 12/28/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
sidewalk and driveway approach repoured - sidewalk area in spec - close permit |
| 12/18/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
was called out to chcek on the removals before repour - CN |
| 12/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
NOV written out and left in matts box - CN |
| 11/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and took pictures of driveway for NOV - per matts request -CN |
| 11/28/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
driveway still not per spec or redone like the contractor said he would do - will get with matt to write NOV -CN |
| 10/22/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
driveway still not done per spec and has not been redone by contractor - CN |
| 09/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
checked driveway that was poured yesterday it was out of spec and will need to be removed and replaced - CN |
| 09/25/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and looked at the driveway layout and the SG compaction - CN |
| 09/19/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre-con, went over details , barricading - CN |