Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 12/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work completed - close permit |
| 12/11/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
looked at the sidewalk alignment again - had them change one side so they could pour it - CN |
| 12/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with pete and permit holder to talk about the layout for the sidewalk alignment - they hadnt layed it out like pete had directed them to last week - CN |
| 11/30/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pete and i stopped by and looked at it he said the sidewalk transition cant be more then 3 to 1 and needs to be fixed it - called terry and made sure that they knew they needed to fix it - he said that he would get with the concrete guy and then call me - CN |
| 11/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
looked at the driveway - the score joints were wrong and the sidewalk alignment werent what we had originally talked about- will have pete come out and look at it - CN |
| 10/23/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no sign of work - CN |
| 10/09/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with forman, concrete guy & designer - talked about issues with the job - CN |
| 09/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre-con - talked about the sewer MH being in the way and shifting the sidewalk and driveway closer to the street - CN |