Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/08/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
sewer line installed and area temp patched. all asphalt will be repaved when the bridge is complete. Permit work is limited to a small right of way area. This project is a ADOT job. I talked with Mike Lynch at FNF construction and he will reopen permits if neccessary. |
| 01/16/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Area still plated on Ajo, needs aspahlt repair |
| 12/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
area still not paved back - a few areas of sidewalk removed without having sidewalk closed signs up - CN |
| 11/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
area still not paved back - a few areas of sidewalk removed without having sidewalk closed signs up - CN |
| 10/17/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
area still not paved back - a few areas of sidewalk removed without having sidewalk closed signs up - CN |
| 09/12/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
had pete come out he talked to FNF - he asked them to clean up valley rd - temp patch new MH and place waddles around stock piles - also asked them to renew there permit - I talked with mike from adot about getting an extended permit for the job - CN |
| 08/07/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
traffic control up and crews are working - CN |