Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 08/14/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Punch list is complete and no issues. Job complete |
| 03/20/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Had a walk through today on site, punch list was given to contractor, and another walk through will scheduled in a week |
| 12/04/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
working along santa rita - CN |
| 10/25/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
working at 14th and santa rita - CN |
| 10/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
was called out on a question about paving on 14th and highland, they wanted to pave with out saw cutting and i said that it wasnt allowed and had pete come out - by time pete got there they had lined up a saw cutting company inorder to pave the area - CN |
| 09/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and checked on the boring across broadway - CN |
| 09/24/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
had them put cold patch on a couple plates on santa rita south of man love - they plan on boreing broadway on tuesday - CN |
| 09/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
looked at paved area on 16th, also talked about work to be done on santa rita and broadway and crossing broadway - CN |
| 08/22/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they had started to weld pipe together - the traffic control looked good - CN |
| 08/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre-con - talked about what the city expects - traffic control and closures - CN |