Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/13/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work completed - close permit |
| 08/02/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they are going to pour slurry today and then pave tomorrow - CN |
| 08/01/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
both services done - temp patch in rdwy will be fixed with in the month per matt - CN |
| 07/24/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they had started on the south service - they were fighting a leaking fitting - eric from tucson water was on site - CN |
| 07/19/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
started working on the north most water line - they got into concrete in the roadway and i informed matt with tricon that they would have to replace the concrete base - CN |
| 07/18/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre con went over expectations - dan was present |