Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 10/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Project Complete. Final and Approved. |
| 09/24/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
All ROW work complete. Will do final inspection after cleanup and Barricades are removed. |
| 09/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Paving complete. Needs Manhole Collar and sidewalk tie ins for completion in ROW. |
| 08/28/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Form check. Adjustments needed on western ADA ramp on northern entrance to meet PAG requirements. Pour scheduled for 10am 8/29. |
| 08/23/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Curb in along ROW. Forming SW and curb transitions. |
| 08/15/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Removals of curb and asphalt today. Form and Pour curb 8/16 |
| 07/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Precon with Granite. |