Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2018 | TDOT-EXCAV GENERAL INSPECTION | Approved | WORK HAS BEEN COMPLETED NO ISSUES AT THIS TIME |
|
| 08/28/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | WORK HAS BEEN COMPLETED EXCEPT FOR LANDSCAPING | |
| 08/23/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ALL SIDEWALK AND ASPHALT WORK HAS BEEN COMPLETED LANDSCAPING STILL NEEDS TO BE COMPLETED |
|
| 08/21/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | PERMIT HAS BEEN RENEWED DRIVEWAY CROSS SLOPE IS GOOD SUBGRADE FOR SIDEWALK IS GOOD |
|
| 08/16/2018 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | TOLD CONTRACTOR TO RENEW PERMIT CONTRACTOR ON SITE. WORKING SIDEWALK AND DRIVEWAY |
|
| 08/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR IS ON SITE | |
| 08/07/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR IS ON SITE | |
| 06/20/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | NO WORK VISABLE AT THIS TIME |