| 10/04/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
all work completed - close permit |
| 09/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and checked sidewalk and ramps - 2 panels were out of spec contractor was informed and said that he would get them fixed - CN |
| 09/20/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and checked sidewalk SG, wiremess install and start of pour - CN |
| 09/14/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor called me out to the jobsite and asked questions about sidewalk alignment - CN |
| 09/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
water work stated on this permit not being done by the permit holder - will be done by tricon on permit # T18RW03795 - CN |
| 09/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
driveway was inspected and was in spec - CN |
| 09/04/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pouring driveway entrance - CN |
| 08/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
had the curb formed up for the driveway - forms and grade looked good - CN |
| 08/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they were going to start curb saw cuts today that they talked about with pete - CN |
| 08/21/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
talked about shifting ramp openings at new driveway due to electrical box - CN |
| 07/31/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre-con talked about expectations for water tap in the middle lane of valencia - including milled in plates and remill of roadway - CN |
| 07/25/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no sign of work in row - asked permit holder to renew his permit as they hadnt started in the row - we also talked about spec's and expectedions for the job - CN |
| 06/20/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no sign of work - CN |