Inspection History Details
Inspection Status: Correction Required
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/10/2019 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | NO FUTHER WORK HAS BEEN DONE | |
| 01/14/2019 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | PERMIT HAS EXPIRED WAITING ON INFO FROM TUCSON WATER AS TO WHO WILL BE PAVING AND WHEN |
|
| 01/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | PERMIT HAS EXPIRED TALKED TO DONNY RUSSEL AND THE POWERS THAT BE ARE TRYING TO FIGURE OUT WHO WILL DO THE FOG SEAL |
|
| 12/11/2018 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | PERMIT HAS EXPIRED WATER VALVES ARE A LITTLE HIGH DONNY RUSSEL SAYS THEY ARE GOING TO MICRO SEAL AREA DAVID STIFFEY IS GOING TO CHECK IT OUT FOR ME |
|
| 09/14/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | CONTRACTOR NEEDS TO CLEAN A FEW METER BOXES | |
| 08/23/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR IS IN THE AREA | |
| 08/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR IS IN THE AREA | |
| 06/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRICON IS IN THE AREA | |
| 06/12/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | BACKFILL IS BEING PLACED IN LAYERS. WATER IS BEING ADDED. COMPACTION IS BEING DONE WITH A JUMPING JACK | |
| 06/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ON SITE, TRAFFIC CONTROL IS UP | |
| 06/05/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRICON STARTED MILLING TODAY ON SAHURA |