Permit: T18RW01947

Parcel: 138213320

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
12/10/2018 TDOT-EXCAV GENERAL INSPECTION Approved work completed - close permit
11/28/2018 TDOT-EXCAV GENERAL INSPECTION Continued checked new ramp layout and sidewalk that they have formed up - they plan to pour today - CN
11/27/2018 TDOT-EXCAV GENERAL INSPECTION Continued helped them with the ramp and sidewalk layout - they want to pour area tomorrow - CN
11/09/2018 TDOT-EXCAV GENERAL INSPECTION Continued layout for sidewalk and ramp/landing were not setup as we talked about - they will re do it and call me back out - CN
11/05/2018 TDOT-EXCAV GENERAL INSPECTION Continued no sign of work - CN
10/12/2018 TDOT-EXCAV GENERAL INSPECTION Continued had a meeting with concrete sub and permit holder about sidewalk - CN
10/02/2018 TDOT-EXCAV GENERAL INSPECTION Continued asked them to renew the permit as the sidewalk hasnt been poured - CN
07/20/2018 TDOT-EXCAV GENERAL INSPECTION Continued driveway was poured in spec they still need to pour sidewalk - CN
06/22/2018 TDOT-EXCAV GENERAL INSPECTION Continued looked at the compacted sg for the driveway and sidewalk also looked at the layout - CN
06/14/2018 TDOT-EXCAV GENERAL INSPECTION Continued looked at the forms they had started gave them some suggestions to make it work and be compliant -CN
05/02/2018 TDOT-EXCAV GENERAL INSPECTION Continued pre-con, they have some issues with the tep pole and gound wire- CN