Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/28/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work is complete. Did a walk through today all asphalt patches look good. only 2 areas of concrete were disturbed. 6 LF of sidewalk. reminded Austin from Fugal that expantion is needed where old concrete meets new concrete, only one side has expantion, also informed Austin that when or where ever concrete was removed that it needed to be removed to the nearest joint. One existing driveway had a patch. A small punch list was given to clean up some alleys, removing a small pile of material and waddles, and to restrip areas on Mission and 36th. |
| 02/28/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
|
| 12/27/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor working on 36th and mission - CN |
| 12/14/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with contractor about paving and temp patches along 36th and mission - CN |
| 11/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
talked with contractor about temp patch at 36 and mission and permit renewal - CN |
| 10/23/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
working various locations - CN |
| 10/16/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
talked with forman about dressing up the plates - night work and when he thought mission and 36th might be done - CN |
| 09/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
plates installed along mission road - will continue night work next week - CN |
| 08/17/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
pre-con about work to be done on mission rd - talked about traffic setup and night work - CN |
| 08/13/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
crews working jobsite - CN |
| 07/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
working various locations - CN |
| 06/19/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with contractor to look at an alley way to see if it needed to be repaved- alley way only had a few areas of pavement none of which the contractor was digging in - CN |
| 05/24/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
working various locations - CN |