Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2018 | TDOT-EXCAV GENERAL INSPECTION | Approved | ALL WORK COMPLETE NO ISSUES | |
| 05/17/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRAFFIC CONTROL IS OK | |
| 05/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRAFFIC CONTROL IS STARTED EXCAVATION OF RIGHT TURN LANE | |
| 05/04/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRAFFIC CONTROL IS GOOD | |
| 04/25/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRAFFIC CONTROL ON SHOULDER | |
| 04/24/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/23/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/17/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/11/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/09/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/28/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | NOT IN ROADWAY | |
| 03/26/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | PRECON FOR SEWER TRAFFIC CONTROL IS ONLY WORK IN ROW |