Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/08/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
6x12 perm patch in area. work complete |
| 12/12/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
still needs perm patch - New permit number T18RW05252 - CN |
| 11/13/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
patch work still needs to be done - email tucson water and notifiy matt again on this one - CN |
| 10/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
follow up on matts email that was sent as the patch still hasnt been fixed correctly - CN |
| 09/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
patch work needs to be redone correctly - email tucson water - talked with matt about this job and he will email tucson water - CN |
| 07/30/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
patch still needs to be done - i will send tucson water another email to get it fixed - CN |
| 06/25/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
still needs perm patch - tucson water emailed - CN |
| 05/16/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
water patch still needs to be done - CN |
| 03/07/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
will send an email to tucson water to fix area because its only temp patch - CN |