Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work completed - close permit |
| 03/13/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with matt and showed him some items that KE&G seems to be having an issue in replacing that were damaged in the sewer bypass job - CN |
| 03/09/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and looked at the stuff they are replacing that were out of spec. there was 2 areas that al said he would have to get with his bosses to approve for replacement. i talked with matt and he said that we would go out on monday and look at those areas - CN |
| 02/12/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
work along 36th looks good, but ramps and sidewalk and patching along euclid from 39th to 33rd not in spec per ada. I infromed matt he said that he would write and NOV. CN |
| 02/12/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- matt asked me to go back out and document all locations that are out of spec so that he can note them on the NOV - CN |
| 02/06/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- talked with nohe from ke&G and asked him to remove or ad the message boardson park to there tcp for paving/striping on 36th - CN |