Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/06/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
slopes were close, pete okayed the work done and said it was better then what we had and to go ahead and close it out- Close permit |
| 01/29/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
panels were repoured and they were out of spec again had pete come out and take a look. he also spoke with the contractor and let them know that they would need to remove and replace it again. they will let me know when they have it redone - CN |
| 01/22/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
checked slopes and they were out of spec, had contractor confirm whith his level which was set to degree's not % which is why they were out of spec. he will remove area poured and get it repoured - CN |
| 01/19/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
helped them lay the sidewalk and driveway wing out and asked for the SG to be compacted before they pour- CN |
| 01/18/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
stopped by and and looked at the damaged sidewalk that needed to be replaced, talked with the contractor about ada specs. he said he would pour tomorrow - CN |