Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T18RW00187
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/03/2018 | TDOT-EXCAV GENERAL INSPECTION | Approved | area was repaved - CLose permit | |
03/28/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | contractor called me to tell me that they are repaving the drivway that was out of spec per ada. I stopped by and they were still doing the removal of the existing. They had also repoured 2 panels of concrete that was out of spec - CN | |
03/09/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | contractor called me and he said that he would like to have a meeting again onsite with his subs to talk about the work that needs to be redone. I had pete come out with me so that he could see the issues with the driveway and the 2 panels of sidewalk that needed to removed and replaced. pete agreed with what i had pointed out as being out of spec and the contractor said that he would get it all fixed. | |
03/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | had a meeting with the contractor at 110:30am to talk about 2 sidewalk panels that needed to be replaced, we also talked about an area of the driveway asphalt that needs to be replaced as it doesnt meet ada requirements - CN | |
01/30/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | went out and checked the ramps and sidewalk was good, tucson water will be removing at least 1 panel in roxw that will need to be rechecked - CN | |
01/17/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | went out and inspected the sidewalk and ramps showed them a few issues to be fixed - CN | |
01/11/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | meet with the contractor and concrete sub to make sure they understood the new ramp designs before they were to pour today - CN - 8am to 8:40 am | |
01/10/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | meet with the contractor about curb forms and made sure that he knew he needed to follow the 2015 standards. contractor and his sub was told to look up the specs as they didnt have them before they poured the curb in row tomorrow - CN |