| 02/01/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved | Inspections done by Jack Kokot, PIA inspector | |
| 05/25/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | called jack and he said that they are still working | |
| 02/27/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Shoulder work continues with daytime TC set up | |
| 02/09/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | 2nd Utility patch complete working in shoulder area | |
| 02/08/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pave 2nd utility crossing | |
| 02/07/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Utility crossing continues | |
| 02/06/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Start 2nd utility crossing on S/Side of Starr Pass on Greasewood | |
| 02/06/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Start 2nd utility crossing on Greasewood on S/Side of Starr Pass at intersection | |
| 02/02/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Crew potholing for 2nd utility crossing S/W corner Greasewood and Starr Pass | |
| 01/31/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pave utility crossing on Greasewood | |
| 01/30/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Began utility crossing on Greasewood 500 FT south of Starr Pass Work monitored with PIA permit T17PI00034 work |
|
| 01/24/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working on water line S/B Bike lane and shoulder. TWater insp. Eddie Frias on site Work monitored under PIA #T17PI00034 |
|
| 01/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | talked with tom about the utility work he said that pia could watch it - CN |