Permit: T18RW00021

Parcel: 13824022G


Addresses:

1895 W VALENCIA RD

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
08/31/2018 TDOT-EXCAV GENERAL INSPECTION Approved areas that were looked at by pete and i have been replaced - Close permit
07/31/2018 TDOT-EXCAV GENERAL INSPECTION Continued npl onsite milling bad patched areas - CN
07/24/2018 TDOT-EXCAV GENERAL INSPECTION Continued jimmy said he was hoping to start this week on fixing the patches - CN
06/22/2018 TDOT-EXCAV GENERAL INSPECTION Continued pete and i had a meeting with jimmy from NPL & he will replace 4 patches along valencia - CN
06/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued got with jimmy and he said that he would get back with me on a time and day to meet this week to look at the patches that need to be redone - meeting set for friday at 8am - CN
05/22/2018 TDOT-EXCAV GENERAL INSPECTION Continued Meet with jimmy from npl showed him 4 bad patches along valencia from the pizza hut to the big o tire- i recommened that they use a straight edge while paving and when they repave these areas- CN
05/03/2018 TDOT-EXCAV GENERAL INSPECTION Continued no work going on, not all patching complete -CN
04/27/2018 TDOT-EXCAV GENERAL INSPECTION Continued - drove the patches done by NPL they are still rough. i asked matt to drive them over the weekend so that i could get another opinion on it before telling NPL to redo it - CN
04/18/2018 TDOT-EXCAV GENERAL INSPECTION Continued called jimmy with NPL and let him know that when i drove the first couple of patches they did and they were a little rough over by pizza hut - CN
04/03/2018 TDOT-EXCAV GENERAL INSPECTION Continued meet with jimmy from npl and they had started paving and dowling, pouring concrete along valencia. work is slow going and it will take them another 3 weeks or so to finish - CN
02/26/2018 TDOT-EXCAV GENERAL INSPECTION Continued - meet with npl jimmy, pete and myself to go over paving and concrete patching on valencia - CN
02/23/2018 TDOT-EXCAV GENERAL INSPECTION Continued - working on gas tie ins - CN
02/12/2018 TDOT-EXCAV GENERAL INSPECTION Continued - had a meeting with SWG and bryan from npl , pete , myself to talk about the driveway @ headly "patch" issue. the resolution was pushed higher to david, lance and matt - CN
01/30/2018 TDOT-EXCAV GENERAL INSPECTION Continued NPL installing gas line along valencia - CN