Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
Permit Number - T18CM10091
Inspection Description - FRAMING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/18/2020 | FRAMING | Approved | Approved. | |
08/10/2020 | FRAMING | Partial Approval | Partial , Framing for Elevator Shaft for all 4 levels ok to Sheetrock. Framing and lining for Mechanical shaft located @ GL 11-E all four levels ok to Proceed. | |
07/21/2020 | FRAMING | Partial Approval | partial 1- Third Floor fur out is okay to sheet rock. |
|
07/17/2020 | FRAMING | Partial Approval | Partial, Framing 2nd floor corridor Fire stop in place ok to proceed. | |
06/23/2020 | FRAMING | Partial Approval | , partial 1- This inspection is for the entire Third Floor only. |
|
06/04/2020 | FRAMING | Partial Approval | Partial, Electrical rooms 4 floors, Walls ok to sheet one side to surface mount Equipment. | |
06/01/2020 | FRAMING | Partial Approval | partial 1- Lobby ceiling area is okay for first layer of sheet rock., |
|
05/22/2020 | FRAMING | Partial Approval | Partial, 4th Floor Corridor Deck framing . | |
05/18/2020 | FRAMING | Partial Approval | partial 1- Exterior Zip system sheathing and shear wall nailing is okay for all floors to tape and seal. |
|
05/13/2020 | FRAMING | Partial Approval | 1- 3rd Floor Corridor deck from grid line 1 to 20 is okay to cover. | |
05/01/2020 | FRAMING | Partial Approval | 1- First Floor Corridor ceiling from grid line 1 thru 14 is okay for sheet rock. 2- Second Floor Corridor ceiling from grid line 1 thru 20 is okay for sheet rock. |