Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
Permit Number - T18CM09862
Inspection Description - PLUMBING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/28/2018 | PLUMBING - FINAL | Approved | ||
| 12/27/2018 | PLUMBING - FINAL | Correction Required | 3/4” T&P drain line required Secure gas line to wall in w:H Closet Install missing J/box cover 6” Clearance required for appliance connectors at B Vent B- Vent Clearance at ceiling required of 1” from combustables Vent slope to be 1/4” per foot towards vent outlet-this is a gravity vent |
|
| 12/24/2018 | PLUMBING - FINAL | Not ready for Inspection | No one on site, Units not addressed or labeled, Rehab project Units not occupied. | |
| 12/21/2018 | PLUMBING - FINAL | Denied | 1- Shall provide (3) sheet metal screws on the water heater draft collar |