Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 06/01/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 12/31/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Rebar for interior fountain. Ok to shot Crete fountain. |
| 10/18/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
Contractor cancelled. |
| 09/26/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Stair well walls at Northwest stairs; column piers for canopy (4), to be dry packed and poured; footings for interior canopy. Ok to place concrete in progress areas. |
| 08/28/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Footings for canopy; epoxied and rebar is in place. Ok to place concrete in progress areas. |