Inspection History Details
Inspection Status: Approved
Inspection History: RESIDENTIAL INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2019 | RESIDENTIAL INTERMEDIATE | Approved | ||
| 03/11/2019 | RESIDENTIAL INTERMEDIATE | Correction Required | 2" waste for master bath needs required 1/4” per ft slope 3" waste for 2nd floor hall bath also needs required slope Install framing for master bath shower then install shower per specs Water test all 2nd floor waste piping Intermediate HVAC AP Intermediate Electrical AP |
|
| 03/11/2019 | RESIDENTIAL INTERMEDIATE | Partial Approval | plumbing inspection | |
| 03/08/2019 | RESIDENTIAL INTERMEDIATE | Not ready for Inspection | ELECTRICAL WORK TO BE DONE |