Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/13/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 05/09/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Second left 4 feet to 8 feet |
| 05/08/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1- Masonry first lift is okay for grout. |
| 05/07/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Not ready for Inspection |
1- Work is incomplete. |
| 04/29/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1- Steel reinforcement provided for the stem wall, Okay for grout |