Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Approval

Inspection History: PLUMBING - FINAL

Date Description Inspector Results Comments
01/29/2019 PLUMBING - FINAL Partial Approval 1- Shall provide temperature mixing valves for each lavatory.
01/28/2019 PLUMBING - FINAL Partial Approval REVIEW OF WATER DISINFECTION REPORT COMPLETED
01/24/2019 PLUMBING - FINAL Denied 1- Job foreman is no longer working for this company as of 01/23/19. There was no access to the inspection area.
11/29/2018 PLUMBING - FINAL Prior to Final Inspectn WATER DISINFECTION REPORT REQUIRED