Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/28/2018 | REINFORCED MASONRY PRE-GROUT | Approved | 2nd lift ok Gave contractor approval to take pictures of next bond beam shown between this the 2nd lift and final bond beam. pictures sent by text and #4 single bar bond beam approved from pictures. | |
| 12/24/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | first lift OK to pour. Make sure to add wall ties at required spacing. | |
| 12/20/2018 | REINFORCED MASONRY PRE-GROUT | Correction Required | No plans on site Romex is not allowed in masonry. Please use UF cable or another type of cable Approved for this use. |