| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/24/2019 | ENGINEERING - FINAL | Approved | ||
| 07/23/2019 | ENGINEERING - FINAL | Partial Approval | Complete development package work. No issues that would prevent a temp c of o | |
| 07/12/2019 | ENGINEERING - FINAL | Not ready for Inspection | Engineering has no issues that would prevent a temporary certificate of occupancy. Complete all the work shown in your development package plan; landscaping and striping. |
|
| 04/29/2019 | ENGINEERING - FINAL | Not ready for Inspection | Inspection of trash enclosure footings. I instructed Mike to use his development package permit for the inspections. DP 18-0233 |