Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 11/26/2019 |
PLUMBING - ABOVE CEILING |
|
Approved |
|
| 08/21/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Operating Room #23; plumbing above ceiling is complete. |
| 06/18/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Rooms #950923; 950924. |
| 06/14/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Level #9; Rooms 950913; 950914. |
| 06/10/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Rooms #940123B and 940121 |
| 05/09/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Tower #4, Level #9: Chilled supply and return lines (1”-2”). Ok to insulate progress areas. |
| 05/08/2019 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Heated Hot Water lines at 3/4”-2” lines: East and West at Tower #4; Level#9. Ok to insulate progress areas. |