Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/01/2020 | FIRE - FINAL | Approved | ||
| 02/05/2020 | FIRE - FINAL | Partial Approval | Was waiting on Cintas paperwork, did not show the pre-action system as being monitored. Pre-action system shall be linked to current monitoring system. Fees added. |
|
| 01/31/2020 | FIRE - FINAL | Denied | * Ceiling tiles shall be in place. * Holes in ceiling shall be concealed or new tiles put in. * Exits shall be unobstructed. * Keys for knox box shall be made available. * Area shall be open to install locking caps. * Paperwork for elevator needed from the state. |