Inspection Status: Passed
Inspection History: COT - LCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/09/2021 |
COT - LCBU - Building Progress |
DQUINN |
Approved |
Entered by RSALDAT1 - Ap |
| 02/01/2021 |
COT - LCBU - Building Progress |
DQUINN |
Partial Approval |
Entered by VLEON1 - PARTIAL - Entry lid frame ok, being supported by designed tube steel columns and beams. Roof trusses and hangers match design specs that have yet to be reviewed. No other framing inside shell tilt ups. |
| 12/30/2020 |
COT - LCBU - Building Progress |
DQUINN |
Cancelled |
Entered by VLEON1 - CANCELLED PER JOEL |
| 09/25/2020 |
COT - LCBU - Building Progress |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Closure tilt-ups ok to pour |
| 04/22/2020 |
COT - LCBU - Building Progress |
ESTEVENS |
Partial Approval |
Entered by RSALDAT1 - RVI Tilt up concrete walls for west side of building.
|
| 04/14/2020 |
COT - LCBU - Building Progress |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - RI canceled |
| 03/10/2020 |
COT - LCBU - Building Progress |
DQUINN |
Not ready for Inspection |
Entered by DMERANZ1 - Per contractor at 4052226
|