Permit: T18CM07563

Parcel: 11705033A


Addresses:

340 E 6TH ST


Inspection Status: Approved

Inspection History: ZONING PROGRESS

Permit Number - T18CM07563

Inspection Description - ZONING PROGRESS

Inspection Status - Approved

Date Description Inspector Results Comments
02/18/2022 ZONING PROGRESS Approved ALL ISSUES APPROVED.
09/21/2021 ZONING PROGRESS Partial Approval PARTIAL APPROVAL: PLANNNERS HAVE REVIEWED REPORT SUBMITTED. FINAL ISSUES AND STATUS ARE AS FOLLOWS:

WEST BUILDING:
1). SITE PLAN - STILL NEEDS TO INSTALL BIKE RACKS.
2). BUILDING PERMIT ELEVATIONS - THERE ARE A SERIES OF SMALL VERTICAL WINDOWS THAT ARE NOT PRESENT BUT SHOWS ON BUILDING PLAN ELEVATIONS. PLANNERS ARE DISCUSSING AND RICK IS RESEARCHING DEV PKG FOR MODIFICATIONS SUBMITTALS.
EAST BUILDING:
1). SITE PLAN - BIKE RACKS LACKING ON NORTH ELEVATION.
2). BUILDING PLANS - ELEVATIONS SHOW A SERIES OF SMALL WINDOWS THAT ARE IN ALIGNMENT VERTICALLY COVERING ALL FLOORS. SITE VIEW SHOWS LACKING. PLANNERS ARE DISCUSSING AND RICK IS REVIEWING DEV. PKG FOR MODIFICATION SUMBISSIONS.

NEXT STEP: WILL COMMUNICATE AND WAIT FOR BIKE RACK INSTALLATION. WINDOW ISSUE WILL BE DECIDED BY PLANNERS OR RESEARCH FINDINGS. ALL OTHER ISSUES ARE IN COMPLIANCE FOR ZONING.
09/17/2021 ZONING PROGRESS Partial Approval REPORT SENT TO PLANNERS, STATUS FOR ZONING IS AS FOLLOWS:

T18CM07563 - EAST APT BUILDING: PARTIAL, WINDOWS ON WEST ELEVATION ARE LACKING. WILL REVIEW DOCS AGAIN IN CASE THERE WAS CHANGE BY ARCHITECT.

T19CM05174 - WEST APT BUILDING
1. PARTIAL, THERE ARE A SERIES OF WINDOWS LACKING ALONG THE NORTH AND WEST ELEVATIONS. WILL RE REVIEW DOCS FOR ANY CHANGES SUBMITTED.

T18SA00242 :
1. ELEVATION MATCH APPROVED.
2. RENDERINGS MATCH APPROVED.
3. MATERIALS APPROVED.
4. COLORS APPROVED.

DP18-0067 - PARTIAL APPROVED, LACKING BIKE RACKS ON WEST BUILDING, WEST ELEVATION.
1. SITE PLAN PARIAL APPROVAL.
2. LANDSCAPE APPROVED.
3. HARDSCAPE APPROVED.

HISTORIC:
PARTIAL, WILL DISCUSS WITH HISORIC PLANNERS IF CAN PLAC IN APPROVED. NO SIGNS OF LIFTING, MOVEMENT, DAMAGE OR ANY OTHER VISIBLE CONCERN AS TO INTEGRITY OF HISTORIC DEL SOL BUILDING TO SOUTH OF PROJECT ON 4THAVE.

NEXT STEP: MEET WITH PLANNERS TO DISCUSS.
09/09/2021 ZONING PROGRESS Partial Approval ON SITE REVIEW. NEXT STEP SEND RPT TO ASSOCIATED PLANNERS.
07/24/2021 ZONING PROGRESS Partial Approval CONDUCTED INSPECGTION FOUND ALL ITEMS MATCHING APPROVALS. PROVIDED PP REPORT TO ASSOCIATED REVIWERS. FOLLOWING PROVIDED:

AP - ON SITE VIEWS VS CONTRUCTION DOCS ELEVATIONS.
AP - ON SITE VIEWS VS RENDERING ASSOC WITH BOTH SA PERMITS.
AP - ON SITE VIEWS VS ELEATIONS ASSOC WITH BOTH SA PERMITS.
AP - ON SITE VIEWS VS MATERIALS.

PA - LANDSCAPING
PA- HARDSCAPING
06/03/2021 ZONING PROGRESS Partial Approval PROGRESS CONTINUES, INSPECTION FOUND TWO ELEVATIONS THAT HAD WINDOWS, ARCHITECTURAL DETAIL ALONG ROOF AND COLORS NOT MATCHING RENDERINGS FOR T18SA00242. CREATED REPORT AND SENT TO ASSOCIATED REVIEWERS. ALL OTHER OPENINGS AND ARCHITECTURAL MATCH APPROVED RENDERINGS. HISTORIC INSPECTION HAVE BEEN COMPLETED, NO SIGNS OF DAMAGE (LIFTING, CRACKING, ALL ROOF LINES AND CORNERS STRAIGHT. HISTORIC BUILDING IS SOUTH OF PROJECT AND IS RETAIL STORE.
04/26/2021 ZONING PROGRESS Partial Approval CONDUCTED INSPECTION. PROVIDE UPDATE IN PP REPORT SHOWING PROGRESS.
03/25/2021 ZONING PROGRESS Partial Approval INSPECTION FOUND ALL ITEMS MATCH APPROVALS. PROVIDED PP UPDATE TO ASSOCIATED REVIWERS.
12/03/2020 ZONING PROGRESS Partial Approval INSPECTION FOUND ALL OBSERVABLE IID COMPONANTS MEETING APPROVALS. PROVIDED PP REPORT TO ASSOCATED REVIWERS.