Inspection Status: Approved
Inspection History: PLUMBING - PRE SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 04/02/2021 |
PLUMBING - PRE SLAB |
|
Approved |
AP |
| 02/05/2020 |
PLUMBING - PRE SLAB |
|
Partial Approval |
2 - 2" and 1 - 3" copper potable lines run under the footing at 5.2 - A.4. Ok to backfill. |
| 02/04/2020 |
PLUMBING - PRE SLAB |
|
Not ready for Inspection |
|
| 01/24/2020 |
PLUMBING - PRE SLAB |
|
Not ready for Inspection |
Not under test. |
| 01/23/2020 |
PLUMBING - PRE SLAB |
|
Partial Approval |
Rough plumb ok to backfill in gl 2.5 to 4.1. D.8 to f.1 |