Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 04/02/2021 |
PLUMBING - ROUGH, SOIL |
|
Approved |
AP |
| 03/13/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
4" pvc at west exterior, from E.5 to D at 1.3 ok to backfill |
| 03/05/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Floor drains and 4" pvc lines ok to backfill east and south of double elevator chase. |
| 02/08/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PVC ROUGH (INSP FROM 12PM-2PM) |