Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/18/2022 |
BUILDING - FINAL |
|
Approved |
|
| 02/16/2022 |
BUILDING - FINAL |
|
Partial Approval |
. Partial. Final depending on Engineering and Zoning Finals. Apartment in question are currently occupied. |
| 07/27/2021 |
BUILDING - FINAL |
|
Denied |
DE. 1-Remove scaffold from courtyard. 2-Install fencing around adjacent work area. |
| 07/27/2021 |
BUILDING - FINAL |
|
Partial Approval |
TFD AND ZONE INSPECTIONS OPEN. INSPECTOR AP 1090, NOTES: Mechanical Final-AP. All work on site complete; recommend issuing Temp C of O. |
| 07/14/2021 |
BUILDING - FINAL |
|
Cancelled |
CA |