Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T18CM07563
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/14/2021 | BUILDING PRE-SLAB | Approved | AP | |
03/03/2020 | BUILDING PRE-SLAB | Partial Approval | NW corner ground floor unit slab ok to pour. | |
02/18/2020 | BUILDING PRE-SLAB | Partial Approval | Slabs gl 2 - 5 to A.1 - B and 1.8 - 3.1 to D - E.3 Ok to pour |
|
01/29/2020 | BUILDING PRE-SLAB | Partial Approval | E and W stairwells and elevator ok to grout 31’4" | |
01/28/2020 | BUILDING PRE-SLAB | Partial Approval | SLAB OK TO POUR AT GL 6 - 4 & C.3 - D.4 | |
01/21/2020 | BUILDING PRE-SLAB | Cancelled | Per super due to rain | |
01/07/2020 | BUILDING PRE-SLAB | Partial Approval | 1st elevated floor, NE quad. - from 5 to 8 and A.1 to D .4 SW corner of this quad, it offsets around east stair well a few x. Ok to pour. |