Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2019 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 03/06/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | changed to PA due to more inspections needed | |
| 03/01/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | west wall on Grid 1 from A to G Elevation from 16’ to 20’ | |
| 02/27/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Up to 16’ on West side | |
| 02/25/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | third lift on west wall from Gridline A to F OK. Fix and center cages to maintain clearances before pour of Caissons and pedestals in front. | |
| 02/21/2019 | REINFORCED MASONRY PRE-GROUT | Cancelled | per phone call from builder. | |
| 02/20/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | West wall, second lift, South half. | |
| 02/19/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK to grout first lift of lower west wall. | |
| 02/12/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK to grout east wall to top of wall | |
| 02/07/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | East wall OK to grout from 16 to 20 feet. | |
| 02/06/2019 | REINFORCED MASONRY PRE-GROUT | Cancelled | ||
| 02/04/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | East side 4th lift | |
| 01/31/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | West upper wall ok to grout 1st lift East wall ok to grout 3rd lift |
|
| 01/30/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 2nd lift GL-6 from B to G only | |
| 01/28/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | first lift on east wall OK |