Inspection Status: Partial Approval
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/14/2019 |
ENGINEERING - FINAL |
|
Partial Approval |
Provide city of Tucson approve revisions for all changes to approve plans for grading and drainage. Overall development package not complete. Remove all construction equipment from site. OK for TCO only at this time. |
| 02/14/2019 |
ENGINEERING - FINAL |
|
Approved |
STEVE, ARMANDO, AND ALEX LOOKED AT DEV PKG. PROPER NOTES IN DEV PKG TO MAKE SURE REVISION AND PROPER APPROVAL OCCURS. |
| 02/12/2019 |
ENGINEERING - FINAL |
|
Continued |
provide revision for accessible path to Old Vail Rd. Remove all construction equipment from site |
| 02/12/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
complete all work on approved plans. Repair parking spot ADA over 2%. Provide CERT letter for all grading and drainage. Access to Street provide revision for changes |
| 02/11/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
provide revisedPlans for accessible path to old Vail Road. Remove all construction equipment from site. Provide certification letter for all drainage and grading for site from engineer of record. Repair slopes to accessible parking |
| 02/08/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
ADA parking over 2%.Complete sidewalk from street to building on a proof plan |
| 12/19/2018 |
ENGINEERING - FINAL |
|
Continued |
Rebar in walls for trash enclosure okay. |
| 11/21/2018 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
Complete all work on development package plans before calling for engineering final. |
| 11/16/2018 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
Complete rebar in footer for trash enclosure for this inspection. |