Permit: T18CM06524

Parcel: 14002010A

Inspection Status: Partial Approval

Inspection History: ELECTRIC - UNDERGROUND

Date Description Inspector Results Comments
02/06/2019 ELECTRIC - UNDERGROUND Partial Approval 9-4" PVC Conduits Between Line 1 and 2 at Ciller Room
12/18/2018 ELECTRIC - UNDERGROUND Partial Approval Room 1.02.04 West Electric Room
16-3" Conduits, 4-4" Conduits, and 5-11/2" Conduits for Subpanels
16 Floor Boxes for open work stations, 3 single floor boxes for single stations
11/30/2018 ELECTRIC - UNDERGROUND Partial Approval 9-4" PVC Conduits East Electric Room
1-3" PVC Conduits Between D and E
2-3" PVC Conduits East to West @ D and E
2-3" PVC Conduits South to North
2-4" PVC Conduits South to North
2-3" PVC Conduits R South and L South
13-1" PVC Conduits East Panel
11/28/2018 ELECTRIC - UNDERGROUND Partial Approval 10-4" Conduits from Trans to distrubution panels in Electrical Room
2-3" " " " " " " " " "
1-11/2" " " " " " " " " "
These are from the service to the Electrical Room on the West Side
!! 1" Conduits for Home Runs from Panels to the North and to Main Electrical Room
11/19/2018 ELECTRIC - UNDERGROUND Partial Approval 11- 1" Conduits between lines 14 thru 17
8- 3/4" Conduits between D and E going to East electrical room
4- 1" and 1- 11/4" Conduits to same.
11/15/2018 ELECTRIC - UNDERGROUND Partial Approval 2-1",1-11/4", 10-4", 1-3" Conduits from Grids 13-15 Between lines B and C, 1-4" to Main Distrubution Room Grid 15 Between lines B and C
11/14/2018 ELECTRIC - UNDERGROUND Partial Approval 4 underground J boxes and conduit at column line 6.5 to 7.5 north and south of grid line C.
Underground conduit between column line 2 and 3 and between B and C.
11/09/2018 ELECTRIC - UNDERGROUND Partial Approval 10-4 inch PVC conduit for secondary
1- 3" and 1-1" as well
11/08/2018 ELECTRIC - UNDERGROUND Partial Approval conduit between C&D also 5 and 3. One inch branch circuits, 11/4" Bonds and Ground.
10- 3/4" & 1" PVC Home Runs from Elec Room at Line D Between 3&4. 3 3/4" Conduits for Home Runs
11/05/2018 ELECTRIC - UNDERGROUND Partial Approval column line 6 electric conduit
11/02/2018 ELECTRIC - UNDERGROUND Approved 15 three-quarter inch PVC conduit’s for homeruns to circuits electrical room
10/31/2018 ELECTRIC - UNDERGROUND Partial Approval 80 feet with 64 inch PVC to 2 inch PVC conduit between lines C and D
10/30/2018 ELECTRIC - UNDERGROUND Partial Approval 9 4"PVC Conduits for future use
10/30/2018 ELECTRIC - UNDERGROUND Partial Approval 10 4" PVC Conduits for Generator
10/29/2018 ELECTRIC - UNDERGROUND Cancelled
10/26/2018 ELECTRIC - UNDERGROUND Partial Approval 10-4" PVC Conduits with Ridgid Sweeps at Electrical Room West
10/25/2018 ELECTRIC - UNDERGROUND Partial Approval 10-4 PVC Conduits for Secondaries
10/23/2018 ELECTRIC - UNDERGROUND Partial Approval four-inch PVC conduits for switchgear number two
10/19/2018 ELECTRIC - UNDERGROUND Partial Approval 10 4 inch PVC conduit on the west side running south for secondaries
10/18/2018 ELECTRIC - UNDERGROUND Partial Approval Between four and six in B and C Inclusive
10 4 inch PVC conduit one 3 inch and one 1”
10/18/2018 ELECTRIC - UNDERGROUND Partial Approval Secondaries 10 4 inch PVC conduit west running south
These inspections were done for power Inc. contractor for TEP and Ashton
10/16/2018 ELECTRIC - UNDERGROUND Partial Approval 20 1010 4 inch one 3 inch and 11 inch PVC underground conduit extending from grid lines 9 through 16
10/16/2018 ELECTRIC - UNDERGROUND Not ready for Inspection washed out due to rain
10/09/2018 ELECTRIC - UNDERGROUND Partial Approval 10-4 inch PVC conduit, 1- 3 inch conduit from control room 1.02.04 Line 3 to control room 1.1707-18