Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/13/2019 |
PLUMBING - FINAL |
|
Approved |
See attached letter head wildcat Plumbing |
| 12/05/2018 |
PLUMBING - FINAL |
|
Partial Approval |
need drawings on site at time of inspection. Another floor sink may be needed for ice cream fridge as condensate line is not meeting the needed slope and it is sitting on the floor. All ABS or PVC piping needs to be 6" above the kitchen floor where possible, if not possible due to conditions as high as possible. |