Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 07/12/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 02/08/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
install dowels into wall footing. Make sure 3 inch clearance around bars before pour. Garage footings OK to pour. |
| 01/22/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Residential duplex: more footings and electric underground later for the garages in the back today’s inspection is for the main building |
| 01/10/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
for fence only not for building |
| 01/10/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
for fence only not building |