Permit: T18CM05941

Parcel: 13609014B

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
08/08/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
04/10/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Retaining wall, east of sanctuary, ok to pour.
03/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pad for high school worship area
03/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stem Wall east side of mezzanine, footing and steel and pad
03/08/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval West mezzanine footing with 2 #5 bottom 1 #4 top with #4 48" oc
03/07/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 8 boxes/footings with rebar for columns
5 footers with rebar for pad pour
03/06/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5 additional column piers per plans
changed from AP to PA per GWEST due to more work to be done
03/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3’ X 3’ Footings on east side #5 12" EW horizontal and 4# 5 verts with 2 #4 wraps
03/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 13 column bases with #5 Bert’s and 5#4 wrapped around per plan
03/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval High School Stage Wall
Please open the 1005 line back up and call Bills AP a PA as lots of rebar to go
02/26/2019 EXCAVATION/LAYOUT REBAR & ZON Approved