Permit: T18CM05873

Parcel: 140252690


Addresses:

5904 S ALVORD PL

Inspection Status: Approved

Inspection History: PLUMBING - GAS PRESS TEST FNL

Date Description Inspector Results Comments
12/13/2018 PLUMBING - GAS PRESS TEST FNL Approved OK to clear gas for new service
12/10/2018 PLUMBING - GAS PRESS TEST FNL Denied Work not complete enough to inspect
12/07/2018 PLUMBING - GAS PRESS TEST FNL Denied Provide gas bond
complete water heater install install
anti tilt stove
next denial will result in a refee
11/28/2018 PLUMBING - GAS PRESS TEST FNL Not ready for Inspection no pressure on gauge. Need gas Bond. Need water heater and furnace installed.