Permit: T18CM05190

Parcel: 14002010A

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
09/26/2019 MECHANICAL - INTERMEDIATE Approved
09/24/2019 MECHANICAL - INTERMEDIATE Partial Approval 2nd floor west above drop mechanical ok to cover
09/13/2019 MECHANICAL - INTERMEDIATE Partial Approval
08/13/2019 MECHANICAL - INTERMEDIATE Partial Approval 2nd floor main supply in center of building from Grids 2 to 7, ok to insulate
06/12/2019 MECHANICAL - INTERMEDIATE Partial Approval Bldg 1 chill h2o a - c 100lbs pressure on hydrostatic test -ok back to central plant with 6" mains.
05/30/2019 MECHANICAL - INTERMEDIATE Partial Approval Bldg 1 - 2nd floor - east to west vav complete and ok to wrap.
05/29/2019 MECHANICAL - INTERMEDIATE Cancelled Arrived on site at 4pm. Mech contractor gone. Has been rescheduled for tomorrow 5/30/2019
02/26/2019 MECHANICAL - INTERMEDIATE Partial Approval 6” to 2” main header water test at 100 psi ok