Permit: T18CM05190

Parcel: 14002010A

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
09/26/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
05/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North, South and middle slabs ok to pour in East canopy.
05/20/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
05/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stairwells 2 3 slabs and curb footings ok to pour
04/30/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
04/15/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 - f1 footings at west end of canopy ok
04/12/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
04/09/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 chiller pads ok to pour
04/08/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
04/02/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 remaining west transformer pads and ufer ok to pour
04/01/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
04/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Line b - 21 and 22 f3 footings ok to pour
Line e - 20 and 21 f3 footings ok to pou
03/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 8 f1 footings for east canopy posts. Gl 22. B to f
2 f3 footings at 21 d and 21 e
Ses room footings and slab ok to pour between lines 1 and 2
03/28/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
03/27/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
03/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ok to pour 3 footings for west Transformer containment storage
03/19/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
03/18/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ok to pour footings on Grid F from 3 to 15
03/15/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
02/04/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Job site not ready after rains
02/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Entry Made to Reset from AP to PA, for inspections to be scheduled
02/01/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
01/31/2019 EXCAVATION/LAYOUT REBAR & ZON Approved 7-12 B-D 6" mesh with 12" overlap, 2#5 Bars around perimeter and 2#4 Bars around each opening.
(Arrived at 7:40 No one available in either trailer
Called Troy left message 3 calls
Left at 8:25 other inspections promised)
12/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2-12"EW#6 with 8x12 #5 6"EW for G1,G2,G3,G4and G%
2-12"EW #6 5x8 #5 bars 6"EW G6, A6, A5,A4, A#, A2 South
2-18"EW#6 5x8 #5 Bars 6" EWF,E,D,C.B North
2-12"EW #6 5X7 #6 Bars A
2-18" EW#6 B, C, D, E, F
12/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2-12"EW #6 8X12 Bars #5 6"EW, G1, G2, G3, G4 Same
2-12EW #6 5X8 Bars #5 6"EW, South G6, A6, A5, A4, A3, A2 With 2 Ballard Sleeves.
2-18"EW #6 5X8 Bars #5 6"EW North F, E, D, C, B
2-12"EW#6 EW A
2-18" EW #6 6X7 Bars #5 6EW B,C,D,E,F
12/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
12/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ERFT Pit #6 12”OC EW with Verts to FF