Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T18CM05190
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
05/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | North, South and middle slabs ok to pour in East canopy. | |
05/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
05/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Stairwells 2 3 slabs and curb footings ok to pour | |
04/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
04/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 - f1 footings at west end of canopy ok | |
04/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
04/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 chiller pads ok to pour | |
04/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
04/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 remaining west transformer pads and ufer ok to pour | |
04/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
04/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Line b - 21 and 22 f3 footings ok to pour Line e - 20 and 21 f3 footings ok to pou |
|
03/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 8 f1 footings for east canopy posts. Gl 22. B to f 2 f3 footings at 21 d and 21 e Ses room footings and slab ok to pour between lines 1 and 2 |
|
03/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
03/27/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
03/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ok to pour 3 footings for west Transformer containment storage | |
03/19/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
03/18/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ok to pour footings on Grid F from 3 to 15 | |
03/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Job site not ready after rains | |
02/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Entry Made to Reset from AP to PA, for inspections to be scheduled | |
02/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
01/31/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | 7-12 B-D 6" mesh with 12" overlap, 2#5 Bars around perimeter and 2#4 Bars around each opening. (Arrived at 7:40 No one available in either trailer Called Troy left message 3 calls Left at 8:25 other inspections promised) |
|
12/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2-12"EW#6 with 8x12 #5 6"EW for G1,G2,G3,G4and G% 2-12"EW #6 5x8 #5 bars 6"EW G6, A6, A5,A4, A#, A2 South 2-18"EW#6 5x8 #5 Bars 6" EWF,E,D,C.B North 2-12"EW #6 5X7 #6 Bars A 2-18" EW#6 B, C, D, E, F |
|
12/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2-12"EW #6 8X12 Bars #5 6"EW, G1, G2, G3, G4 Same 2-12EW #6 5X8 Bars #5 6"EW, South G6, A6, A5, A4, A3, A2 With 2 Ballard Sleeves. 2-18"EW #6 5X8 Bars #5 6"EW North F, E, D, C, B 2-12"EW#6 EW A 2-18" EW #6 6X7 Bars #5 6EW B,C,D,E,F |
|
12/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
12/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ERFT Pit #6 12”OC EW with Verts to FF |