Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - YARD WTR LINE/TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/18/2019 | PLUMBING - YARD WTR LINE/TEST | Approved | ||
| 12/05/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Pending chlorine test Replacing water line in mobile home park new 2 inch diameter down to one inch at units 80 through 90. 10 units total |
|
| 11/16/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Lots 20-28 | |
| 11/08/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Units 29 through 45. | |
| 10/31/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Units 46-61. | |
| 10/23/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Units 62 through 78 including the pool | |
| 10/18/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Ok to backfill lines 133 - 151 | |
| 10/05/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | Units 113 - 132 except meters and hose bibbs | |
| 09/07/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | From unit number 10 through unit number 19, plus4 stub outs under the street. | |
| 08/22/2018 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 3" PVC WATER LINE INSTALLED FOR UNITS 91 THRU 99 WITH 1" PEX TO COPPER SERVICES FOR EACH MOBILE HOME |