Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/26/2019 |
ENGINEERING - FINAL |
|
Approved |
APPROVED PER STEVE SHIELDS |
| 07/25/2019 |
ENGINEERING - FINAL |
|
Partial Approval |
Open grading permit for overall site. Provide long-term bicycle parking per approved plans. |
| 04/16/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
This inspection was called in for the approval of the trashing enclosure footer for building number 5. The thought of the trash enclosure was inspected additional rebar was added the footer is approved and ready to be poured, the pouring of this photo will be done tomorrow photos will be provided. |