Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2019 | FIRE - FINAL | Approved | ||
| 01/03/2019 | FIRE - FINAL | Partial Approval | 1. obtain operational permit for HAZ materials. 2. 15" address numbers needed on the bldg. 3. additional reinspection fees added to this permit. |
|
| 01/02/2019 | FIRE - FINAL | Partial Approval | Sprinkler notes. Okay for TCO to move furniture and appliances in. Fire final to be completed when appliances are installed. | |
| 12/28/2018 | FIRE - FINAL | Denied | 1. need sprink final. 2. need alarm final. 3. electrician not on site to test EM lights. 4. obtain operational permit for HAZ materials. 5. add decal over main door, "these doors to remain...." 6. additional reinspection fees added to permit. 7. add address numbers to bldg, 15" numbers. |